Phase 1 is anticipated to last 45 days and will include: closure of the 100 block of S Main St; access to parking and local businesses will be maintained where possible. Lane restrictions along Market Street between Elizabeth Street and Union Street.
The traveling public is encouraged to find an alternate route to avoid potential traffic delays.
The estimated completion date for the ALL-Lima Main Street/Market Street Roundabout Project is November, 2022.